Create a submittal management system that keeps your project on track
Submittals are the documentation backbone of construction quality. A disorganized submittal process leads to delayed approvals, wrong materials, and rework. Here's how to set up and maintain a submittal system that works.
Start by extracting all submittal requirements from the specifications:
Consistent numbering prevents confusion and enables tracking:
[Spec Section]-[Sequence]-[Revision]Example: 08 11 13-001-00
08 11 13 = Hollow Metal Doors and Frames
001 = First submittal in this section
00 = Original submission (01 = first resubmission)
Build the submittal schedule by working backwards from installation dates so review time is on the calendar before material is needed:
Use the same review action codes on every submittal, such as approved, approved as noted, revise and resubmit, and rejected:
Create a folder structure that's easy to navigate:
Submittals/
├── 01_General/
├── 03_Concrete/
├── 05_Metals/
├── 08_Openings/
├── 08 11 13 - HM Doors/
├── 08 11 13-001-00_Shop Dwgs.pdf
├── 08 11 13-001-00_Review.pdf
└── 08 11 13-001-01_Resubmit.pdf
Your submittal log should track these dates for each item:
Review submittal status weekly and issue a report that shows overdue items, items in review, and items still not submitted:
More guides on coordination, reviews, and clean drawing workflows.
Run meetings that resolve open submittal issues.
Create clean markups that move work forward.
Verify submittals match scheduled assemblies.
Match submitted equipment to specified models.