How to prepare for a design coordination meeting

Helonic is an AI construction drawing analysis platform for people prepare coordination meeting during plan review.

Run effective coordination meetings that actually resolve issues

Coordination meetings can either resolve issues or waste everyone's time. The difference is preparation. A well-prepared meeting has a clear agenda, the right people, and documented issues ready for discussion. Here's how to prepare effectively.

How do you define the scope of a coordination meeting?

Focus each meeting on specific areas or issues:

Area-based
Level 2 mechanical room coordination
System-based
Fire protection routing review
Issue-based
Resolving ceiling plenum conflicts
Milestone-based
50% DD coordination review

Trying to cover everything in one meeting leads to shallow discussion and unresolved issues.

Who should attend a coordination meeting?

Only invite people who can contribute or make decisions:

Architect (Project Architect level)
Can make design decisions on the spot
Structural Engineer
For conflicts involving structure
MEP Engineers
Each discipline that has issues under discussion
GC Project Manager
Schedule and budget implications
Trade Foremen
For installation-level coordination

How should you document issues before a coordination meeting?

Document each coordination issue before the meeting with a location, the drawings involved, and a proposed decision:

Issue Documentation Format

Issue #: Sequential number for tracking

Location: Grid lines, floor, area

Description: What is conflicting and why

Disciplines: Who is affected

Visual: Screenshot or markup showing the issue

Proposed Solutions: Options if known

Which documents belong in a coordination meeting packet?

Ensure everyone is working from the same information:

1
Confirm all attendees have the latest drawing set
2
Distribute revised drawings 48+ hours before the meeting
3
Note any sheets that have changed since last meeting
4
Prepare overlay comparisons if helpful
5
Have digital files ready for screen sharing

How should you structure a coordination meeting agenda?

Structure the agenda so high-cost clashes and decisions that block design come first, then routine items:

Review previous action items (5 min)
Quick status check, don't re-discuss
Critical issues first (40-50% of time)
Issues blocking work or requiring decisions
New issues identified (20-30% of time)
Issues discovered since last meeting
Upcoming areas preview (10-15% of time)
Heads-up on next focus areas
Action items recap (5 min)
Confirm assignments and due dates

When should you send the pre-meeting package?

Send materials at least 48 hours before the meeting:

  • Meeting agenda with time allocations
  • Issue log with all items to be discussed
  • Relevant drawing sheets or excerpts
  • Previous meeting minutes and open action items
  • Any RFI responses or ASIs issued since last meeting

How do you prepare a decision framework for a coordination meeting?

Have criteria ready for resolving disputes:

Code requirements are non-negotiable
Safety, egress, accessibility
Gravity wins (things that slope have priority)
Sanitary, storm, condensate
Largest elements route first
Main ducts before branch, mains before laterals
Least flexible routes last
Rigid before flexible
Maintenance access is required
Valves, dampers, equipment

Find issues before the meeting

Walk into coordination meetings with issues already identified. Helonic's AI can scan your drawings and generate a coordination issue report, complete with locations and screenshots, so you can focus meeting time on resolution.